Bheramara 410 MW Combined Cycle Power Plant
Power Plant Location | Bahirchar, Bheramara, Kushtia |
Executive Agency | North West Power Generation Company Limited (An Enterprise of Bangladesh Power Development Board) |
EPC Contractor | M/s. Marubeni Corporation, Japan |
Financer | GOB & JICA |
EPC Cost | USD: 178,788,328; JPY: 10,237,497,008; BDT: 2,562,922,636; EUR: 8,510,300. (Eqv. BDT. 251,998 Lac) |
Total Project Cost | GOB: BDT 91,939.59 Lac plus PA: BDT 322,108.42 Lac |
EPC Contract Signing Date | 16/03/2014 |
Manufacturer of GT and ST | Mitsubishi Hitachi Power Systems (MHPS) |
Fuel Type | Dual Fuel (Natural Gas + HSD) |
Generation Capacity | 410 MW |
Commercial Operation Date | 09/05/2017 (Simple Cycle), 14/12/2017 (Combined Cycle) |
ISO Certification | ISO 9001: 2015, ISO 14001:2015 & ISO 45001:2018 Certified |