Sirajganj 225 MW Combined Cycle Power Plant (Unit-1)
Power Plant Location | Soydabad, Sirajganj |
Executive Agency | North-West Power Generation Company Limited (An Enterprise of Bangladesh Power Development Board) |
EPC Contractor | M/s. China National Machinery Import & Export Corporation (CMC), China |
Financer | GOB & ADB |
EPC Cost | USD 171.77 Million |
Total Project Cost | GOB: BDT 127,848.02 Lac plus PA: BDT 38,046.07 Lac plus NWPGCL: BDT 135.67 Lac |
EPC Contract Signing Date | 12 October, 2010 (Simple Cycle), 08 August, 2012 (Combined Cycle) |
Manufacturer of GT and ST | Siemens (GT), Dongfang Electric Machinery Co. Ltd. (ST) |
Fuel Type | Primary – Natural Gas, Alternative – HSD |
Generation Capacity | 214 MW |
Commercial Operation Date | Simple Cycle: 22 November, 2012 Combined Cycle : 14 July, 2014 |
ISO Certification | ISO 9001: 2015, ISO 14001:2015 & ISO 45001:2018 Certified |