Sirajganj 225 MW Combined Cycle Power Plant (Unit-3)

Sirajganj 225 MW Combined Cycle Power Plant (Unit-3)

Power Plant Location Soydabad, Sirajganj
Executive Agency North-West Power Generation Company Limited
EPC Contractor Consortium of M/s. China National Machinery Import & Export Corporation (CMC), China and Fujian Electric Power Survey & Design Institute (FEDI), China
Financer Standard Chartered Bank (SCB), Siemens Bank GmbH, Bank of China, DeutchePfandbriefbank AG
EPC Cost USD 164.12 Million
Total Project Cost USD 236.22 Million (Equ. BDT 182,856.87) (1USD=77.41 BDT)
EPC Contract Signing Date 12 July, 2015
Manufacturer of GT and ST Siemens (GT)
Dongfang Electric Machinery Co. Ltd. (ST)
Fuel Type Primary - Natural Gas, Alternative - HSD
Generation Capacity 220 MW
Commercial Operation Date Simple Cycle: 09 Aug 2018
Combined Cycle: December 2018 (Expected)