Bheramara CCPP (360 MW)Development Project(Simple Cycle)

Project Location Bahirchar, Bheramara, Kushtia
Executive Agency North-West Power Generation Co. Ltd. (NWPGCL)
Financer GOB & JICA
EPC Contractor M/s Marubeni Corporation, Japan
EPC Cost Eqv. Tk. 251,998 Lac (USD: 178,788,328 ; JPY: 10,237,497,008 ; BDT: 2,562,922,636 ; EUR: 8,510,300)
Total Project Cost Tk. 414,048 Lac (GOB: Tk. 91,939.59 Lac + PA: Tk. 322,108.42 Lac)
Fuel Type Dual Fuel (Natural Gas + HSD)
Manufacturer of GTG Mitsubishi Hitachi Power Systems (MHPS)
EPC Contract Signing Date 16/03/2014
Commercial Operation Date(Completed) 09/05/2017 (Simple Cycle)